Play Video: Open Agenda S2 E26 Executive Misses Work Session Just Prior to Landfill Closure
Show Transcript

Disclaimer: The following transcript was auto-generated and may contain spelling or contextual errors.

You're watching Open Agenda. Here's our
host, Joe White.
>> Welcome to Open Agenda. I'm your host,
Joe White. So, we dropped last week's
episode about the landfill and very
shortly after, uh, Adam Corey from the
acting superintendent of Wakamo County
actually reached out to me and had a
great conversation.
Went out on Friday to to take a tour at
his at his invitation of the landfill. I
got to see a lot of the compliance
issues that he has addressed, but also
really to be there to talk about Cell
Seven and Cell 8 as we're running out of
space. The interview I did with Adam
Corey, I'm going to air as a separate
episode. I've talked to Pack 14 and
they're actually going to air it so that
we don't have too much information in
this one show, but it was a great visit
to talk about the presentation that was
done at the work session on July 15th
and our present concerns. Brought in Mr.
Jim Atkins from Mardella, Mr. Mike
Goldberg from Delmare. Thank you,
gentlemen, for coming out.
>> Glad to be here as always.
>> So, uh you all were at the work session
yesterday with the the county council
and uh Mr. Adam Corey to to hear more
about the the the current issues at the
landfill and the timeline for
construction of cell 7.
>> Yeah.
>> Seemed like it was pretty pretty lately
uh attended by the county executive and
and her administrative staff. Is that is
that
>> No one from the administrative staff was
there. the the highest ranking person, I
guess, would be the the managing
engineer who was the previous person in
charge of the landfill.
>> Yeah. But she didn't
>> she was she didn't participate. She just
sat there and
>> and was not invited up to the table. So
there was no nobody from the executive
management staff including the county
executive herself attended.
>> Well, and you know that's interesting
because on June 30th at the county
executives press conference that was
attended with M Mr. Adam Corey, it kind
of got us this ball rolling. It
definitely seemed like Julie Grodonna
was going to be at that meeting. She she
stated that they were going to have a
work session with the county council to
address the legislative issues.
>> We requested a work session to deal with
this specific issue.
>> This specific issue, we were we were at
a point where we felt most comfortable
after meeting with MDE, after meeting
with our attorney, and this takes a
little bit. This takes a little bit of
time to put something together to really
figure out the best course of action.
So, actually the request was supposed to
go in because we were going to be
meeting in the middle of July for a work
session.
>> This is their last meeting before August
1st when she has a phase closing of the
landfill starting on the first Saturday
in August.
>> Yes.
>> Well, she declared a crisis and then was
awol from, you know, actually doing
something about the crisis. She was
gone.
>> Well, I think I would say um until
there's a crisis, there's really not a
need. So I you we're gonna bring in
Councilman Jeff Merritt to talk about
the the present situation, the leg the
emergency legislation and then also I
want to bring you back in Mike to talk
about the construction that process
because I know that that flows very much
into your work experience and your
background.
But as a lay person, as a citizen, did
you feel like you got the information
that you were looking for after hearing
the county executive's press conference
on June 30th and hearing that we may be
running out of space sooner than later
on the landfill?
>> Well, the press conference left me, you
know, rather, you know, baffled. You
know, there was uh it was at the press
conference that she presented her plan
to phase in closure of the landfill. And
I I'm sorry. I don't know how to put
this gently. That is just the most
ridiculous plan I've ever heard
>> cuz it won't cuz the trash that we don't
bring on Saturday won't magically
shuffle
>> in there. I mean it it it doesn't take
an engineer or a rocket scientist to
understand that. So I have no idea what
her motivations are.
>> There is one other possibility and I'm
going to show some pictures from uh off
of Shavox Road in Forest Grove Road in
Parsonsburg. Uh there's a there's there
and and and the county is working
through this at this point. the
sheriff's office and and the and and and
some of the folks of the county, but
there's a there's a gentleman over there
who is just dumping trash uh in a in a
yard that he actually doesn't own. It's
I just can't even imagine him living
next to this. But this could be our new
reality
>> that Yeah. And that was uh addressed
yesterday by Councilman Holloway to uh
to Adam Corey.
>> Yeah. from about uh
somebody needed to get involved in it
because he was having as a council
person,
>> he was having a hard time getting
anybody to react to it.
>> My understanding is as of Wednesday,
July 16th, uh there is a reaction to it.
So
>> Mr. Cory assured him yesterday that that
he had the right number and the right
person to call to have it addressed. And
so
>> well that that that's that builds
confidence. So what what what's your
what's your takeaway from the
presentation from
>> Well, you know, the the interesting part
about it was it all over the past month
has been a surprise that that we've
gotten in this position. We weren't
here. We were good for 3 to 5 years and
now all of a sudden we're not going to
make the next next year. And
how did this just pop up out of nowhere?
Well, the last five minutes of the
probably hour and a half presentation
was was
a question asked by Councilman Andis.
Plans that were drawn up and approved in
October of 2022.
>> Yeah.
>> Two and a half years ago that were
approved.
>> And he asked this of Adam Cy, correct?
>> Yes.
>> So what was the response?
>> Adam acknowledged that he had found a
document. It was planned and approved in
2022.
>> Cell 7 uh we're expediting the best we
can. Was it in fact um way behind
uh the timeline?
>> Um I actually was reviewing a letter
that I thought about putting into this
slideshow. There was an authorization to
proceed in October of 2022
uh for cell 7. You know, for that
>> authorization to proceed.
>> Yeah. Not necessarily with construction,
but would have started the process we're
working on with DARL. That was October
2022.
>> Now, the permits weren't issued and and
the things that the state needs to do,
but the county had approved that we're
going ahead with cell 7
>> design was deferred uh for about 18
months and that's all throughout the
current executive administration.
>> You know what's interesting there is uh
you talk about the first quarter of
2023. By July of 2023, uh, we were we
were having issues with the confirmation
process of Matt Lights on Heather
Langford and she got up to speak at the
county council meeting in July of 2020.
She was actually very much in charge of
of running the landfill. This is
something that she was doing.
>> Yes,
>> Heather Langford, pretty hot topic of
today's agenda. I have been in the
industry for 16 years. Um, I have a
degree in civil engineering, structural
concentration,
um, mathematics minor. For some reason,
I'm standing here told I'm not deserving
of a position. Right now, no one will be
running public works, the landfill, the
convenience centers, the roads division,
the engineering division, the sanitary
district.
>> I know we have to focus on where we're
at and what's a forward momentum, but we
do need to to talk about what why we got
here. And you're talking about plans
that were put in place before our
current county executive took office, an
actionable plan. Adam Cordy in my in my
uh visit last Friday talked about how
the phase two and phase three permits
were already approved from
>> well you have to look at it whenever you
have a a change in leadership
things fall through the cracks
but in this situation when you went from
admin executive pod to executive Giri
which is when this landfill situation
seems to have fallen through the cracks
act. The only thread that runs through
the entire thing
is the acting director
of public works,
Heather Langford, was in that position
the entire time. So September when the
original drawings were approved and then
when December when Gordono comes into
office, it's the same person running the
landfill the entire time and the same
person who ran it all the way up until
2023 and was so indignant with the
council during public comments that the
council would not approve her being
appointed to deputy director or director
because She didn't have the
qualifications. Well,
excuse me. When when you see the
situation we're in now and she openly
admits that she was in charge of the
landfill in 2022,
apparently she wasn't qualified.
>> And it goes beyond just her admission
that she was in charge of it. I've
reviewed some documents from the
Maryland Department of the Environment
and she is listed as the contact person
for the landfill operation. Well, and
and there is another person too who
deserves some scrutiny and and maybe not
today but but in the near future is
Wayne Strawber.
>> Now, this has come up because the county
council has introducing legislation to
have some level of control or at least
confirmation of professional contracts.
Uh current county executive has hired
him as a consultant for the landfill.
this she even addressed in her
>> well that's one of his his many duties
as he's been I mean he was
>> hired to do the SWAT analysis for the
county he's been been in the landfill I
mean he he's been working for the for
the county as a consultant for over two
years now different projects
>> we're paying a consultant who failed to
perform and we continue to pay a
consultant that same consultant for
additional work on on other issues
>> but he but he wasn't even at the work
session on July 5th He wasn't there.
>> No, but he but he was at the press
conference on June 30. Did we did we pay
for that?
>> And another person who was noticeably
absent is the director of
administration, Bonnke Luffman, who was
also charged with the responsibility of
oversight on the landfill. We have
people in this administration today who
have palpably failed to get this job
done. to Adam Cory's credit and I saw it
with my own eyes noticeable changes out
of the landfill and I even got a chance
to talk to some of the other uh trash
haulers that were there um and and and
and found some positive feedback in that
regard just the the basic operations of
the landfill. But in the meantime, in
the last two and a half years, we have
worked tirelessly, the executive has
worked tirelessly on liquor bills, on
other campaign promises uh that made by
her campaign donor donors and also
running things like Safari.
Well, well, here's the thing. You know,
she's made the statement recently that
she has fulfilled her campaign promises,
but those campaign promises were made to
her friends and her political
contributors. She's also recently made
the statement, and it was at her press
conference, that she's here to represent
the interests of the 104,000 residents
of Wcomako County. Well, you know,
Madame Executive, I I I beg to differ
with you. Yeah, there weren't 104,000 at
the council meeting on on July the 15th,
but there were several county
rep uh residents there that uh did not
see any executive uh office people in
there representing them or or standing
up for him.
>> Well, I want to bring in Councilman Jeff
Merritt and I want to ask him um you
know what he got from the presentation.
He also went on a tour just today, July
16th. of the landfill. And then what I'd
like to do is talk a little bit about
that presentation and the construction
and then come back and and see if the
three of us still have unanswered
questions. Are you all can you all stick
around?
>> I certainly can.
>> All right, Jim, you stay and we'll bring
in Councilman Merritt and uh Mike, we'll
see you in a little bit.
>> Okay,
>> so stay with us with open agenda. When
we come back, we'll have Councilman Jeff
Merritt and we'll get to ask him his
take on the landfill presentation. Stay
with us. We'll be right back.
Welcome back to Open Agenda. And as
we've seen the presentation from Adam
Corey in the Department of Public Works
at the July 15th work session, we still
do have more questions. And I'm sure the
folks out there want to hear how this
phased approach of the landfill closure
may impact them. In order to talk about
that, I brought in Councilman Jeff
Merritt from the second district. Thank
you.
>> And Mr. Jim Atkins from Mardella. Thanks
for sticking around. What amount of
information were you able to get out of
that presentation from Adam Corey and
and and that group from what you were
looking to to find out?
>> I think a lot of the uh the dots were
connected.
>> Okay.
>> Uh we were wondering how serious the
problem was, but looking at the
information that was presented yesterday
in the work session, it is clear that
we're we're in a pretty serious
situation. Um, it was also clear that uh
up until fairly recently we were all
working on information that might not
have been as accurate as we once
thought. Uh, slide that shows geocentex
former. This is on some of the slides
that Mr. Illuminati was showing you as
far as previous estimations on remaining
capacity. um back of the napkin
approach. That was literally a quote um
uh from one of their staff members when
they were on on a retainer for us as an
engineering firm without any over over
um excuse me, aerial survey.
>> Unfortunately, decisions were based on
that information and
uh now here we are.
>> Well, the county executive said uh at
her press conference on June 30th that
she was planning on this work session
with the council. Was she and her uh
administrative uh director of
administration? Were they able to fill
in a lot of the blanks at the
presentation yesterday?
>> They weren't there.
>> I saw pictures of her at the White House
yesterday. So, is this a is this a real
crisis or is this I mean, you're saying
that we're in deep trouble, but is this
a real crisis or not?
>> No, I think this is a real crisis. Okay.
>> Uh I took a tour of the landfill. Um
>> from up on top of the hill, it's very
clear that we don't have a lot of room
left.
>> Okay. And there's another cell that's
yet to be constructed that uh after the
information that we saw yesterday, it
should have begun a year ago.
>> And and and one of the things just to
add on that because I'm sure Councilman
Merritt is uh is trying to be polite
about a few certain things that I don't
have to be polite about.
>> Yeah. But when the uh county executive
calls this a crisis
and says that on uh July the 15th at a
council meeting this is going to be
discussed and then decides to
go to Washington to tour the White
House. Uh no
specific business, county business was
being done apparently, just a tour of
the White House. the director of
administration
uh was not at the council meeting
yesterday. The assistant director of
administration was not at the uh council
meeting yesterday. So,
>> and and assistant the deputy director of
public works wasn't there either.
>> No. No. So, you know,
>> it's excusable that one or or more of
these people may not be there, but
you're you're talking none of those.
>> Yes. And you would think if the county
executive is calling this a crisis,
which truthfully she has spoken the
truth, it is a crisis, okay?
>> That the landfill is going to be full
and might have to close. But where is
everybody? She continues to tout the
lack of communication between the
executive branch and the legislative
branch and the council.
>> When we don't communicate and
collaborate, this is what happens. you
get reactive legislation to share the
information that we have that we've
gathered from Maryland State Department
of Environment working handinhand with
our county attorney making sure that we
are following every state guideline that
we are supposed she had planned to uh
present this to you um that way we could
have a work session in the middle of
July
>> but when she has the opportunity to sit
in a room with the council and discuss a
major problem with the county
>> I think it's important to understand
that the reason we are in this situation
right now with heightened awareness of
the landfill is that um we we had a work
session at the council meeting on June
3rd with um solid waste and it was good
nice presentation. They they gave us
some landfill issues. Um and one week
later there was a plan announced at a
haulers meeting that the council was not
a part of to close the landfill in uh
steps over the next 12 months.
Um because this landfill was filling up
too fast. Um that plan was not
shared with the council on June 3rd, but
it was shared with the haulers on June
10th.
And I think that's important to note
because
um that got everybody's attention and
that's that's what started this
emergency legislation
and now the information is coming out
that we really should have had months
ago.
>> And I want to talk later about your
visit to the landfill. I had also a
great visit with Adam and Corey last
week. But for right now, let's talk
about the the presentation. What part of
that information you said it seems like
we're in some serious trouble or could
be especially if this construction gets
delayed for anything from permitting to
weather.
>> Uh do you feel like the solutions are in
place that the citizens of Wakamaku
County are protected as much as they can
be at this point?
>> I do. Yeah, there there seems to be a
pretty solid plan in place right now. Um
it looks like if everything goes right
that the new cell will be operational in
one year and if that happens we'll be in
good shape. Um Mr. Cory's doing a good
job out at the landfill um filling in
the gaps so to speak.
>> Okay.
>> And making the best use of the space
that we have available in in hopes that
you know we're trying to avoid a closure
of the landfill. If the landfill has to
close, we would have to ship the trash
out of the county and that becomes
expensive. Nobody wants to do that. So,
we're trying to do that uh not do that
at all costs. Avoid doing that at all
costs.
>> One of the major
talking points of this has been out of
county trash coming into the county to
the landfill. Do you feel like there's
progress being made with that with the
landfill and and the county that they're
going to
>> start stopping some of this out of
county trash from filling up the
landfill?
>> It looks like the legislation that's
being currently worked on is going to uh
end up with no outofcount trash is going
to be accepted. Now, uh we're we're
looking at outofcount trash as the the
culprit of all this or at least a major
contributor of all this. But we actually
have no data. Uh there's no there's no
graph. There's no chart. There's no
uh concrete data that says we we have x
number of tons of out of county trash in
our landfill. It's very hard to track
that. Um but it is contributing to the
problem at the landfill. And in order to
conserve space, the measure that we have
to take is to not accept out of county
trash. No, that I mean, Adam Corey has
brought up before that there's a 26%
increase over the last couple years. Uh
I I I think one of the the the terms he
used yesterday was about 5 to 10% of it
was out of county.
>> How much do you think when you tighten
down on the out of county trash, how
much tonnage you think that's going to
um cut?
>> Not 25% of total tonnage.
>> What What do you think will be cut out?
>> Somewhere between 8 and 15%. Uh, one of
the interesting things I did is I when
my visit, I was there a little bit
early. I actually talked to one of the
drivers. Now, this was from one of the
larger haulers and I just asked him um,
you know, one, does he feel like things
are improving at the landfill itself,
like the operations? And and he didn't,
he couldn't go on camera cuz he's on the
clock. Um, but the other question I
asked, I said, "Do you feel like your
route brings trash into this county?"
And I mean, he looked at me, he goes,
"You you can't do that. He you you can't
bring out a county trash here." He goes,
"My company, we have trucks that stay in
Makamako County and some that stay in
Wester County." He says he says, "In in
Delaware, we could never bring somebody
else's trash to that landfill."
>> If we can prevent whatever out of county
trash there is from coming in, it will
help preserve space in our landfill. Do
you did was it addressed at all
yesterday about the timeline of the
permit that the construction permit like
when they're going to apply for it and
maybe even should that it's have been
applied for earlier?
>> Yeah, M. Mr. Cory addressed it yesterday
um where we are on uh just so the public
understands cell is the last cell that
is yet to be constructed on the existing
footprint of the landfill. We are
currently putting trash in cell eight
that appears to have 11 or 12 months
left and then cell 7 in theory might
last 3 years. Cell 7 should have begun
as as I said a year ago.
>> Well, maybe you can clarify or clear
something up. When there was a question
asked of Mr. Corey
about the dates and how long the plans
had been in effect for cell 7.
>> Mhm.
>> And I heard uh I believe I heard 2022
that there was a document that it had
been approved and and passed at 2022. So
is that accurate? And if it is and
nothing is nothing has been done between
2022 and 2025.
>> Cell 7 uh we're expediting the best we
can. Was it in fact um way behind
uh the timeline?
>> Um I actually was reviewing a letter
that I thought about putting into this
slideshow. There was an authorization to
proceed in October of 2022
uh for cell 7, you know, for that
>> authorization to proceed.
>> Yeah. Not necessarily with construction,
but would have started the process we're
working on with DARL. That was October
2022. And that was to begin the
permitting process, the construction
documents and so on way back then, which
normally takes it could take a year or
more.
>> Well, and and at that time, we didn't
have a director of public works, but
there were other folks who were
operating the landfill at that time,
right?
>> And and that's another un bit of
unfortunate situation. We've had five
different people oversee the landfill in
the last two and a half years since
we've all been in office. Um, so as you
can imagine,
>> not at the council's uh not at the
council's direction.
>> No, no, no, no.
>> Okay. I mean, how who who puts that
person in place?
>> Well, the executive.
>> Okay.
>> So, but from from an operational
standpoint, if you can imagine having a
new boss every 6 months, that that
doesn't do much for morale. We have
footage from July of 2023 where Heather
Langford, who's still employed by the
county uh supervisor of of engineers, uh
was stating on her own at at public
comments that that she was at the
landfill. She was running. She was
qualified.
>> Mhm.
>> Uh you're talking about a permit that
was actually started just before our
current county executive was elected.
And then Adam Cordy has spoken to me and
and at the presentation that this permit
this permit the process were started was
just started here recently in in March
of 2025.
>> Mhm.
>> Does that is it reasonable to conclude
there was a lack of oversight from was
was the most material issues being being
addressed at the landfill.
>> I I don't think it was uh if it was we
wouldn't be where we are now. Jim, you
you've you've been very much on top of
the comprehensive plans, the 10-year
plans. Was there a lot of information
that came out of yesterday's
presentation that would surprise someone
who was doing that due diligence you
were doing with the comprehensive plans,
but maybe hadn't had an update in the
last five or 6 months? Yeah, I mean that
yesterday's information was was very uh
informative
because when you look at the most recent
comprehensive plan,
it almost everything where they deal
with municipal waste, residential waste,
commercial waste, industrial waste. It
says in November of 2024 there are no
plans to modify existing practices. So
everything is good. Now the interesting
thing I found about that with the
comprehensive plan is the wording in the
comprehensive plan of November of 2024
is a cut and paste job
>> of the comprehensive plan of 2014.
So, you know, it's a and
>> and you're the second person who's
brought that up to me that this that if
you go back and look at the plan from 10
years ago that the that it looks a lot
like
>> it's it's cut and paste and I mean, you
know, it's just the the same information
is in the same the same plan. I'll be
honest about it. I I've been very
impressed with Mr. Corey the more I'm
the more I listen to him speak. the
county finally has somebody who knows
what they're doing and what they're
looking at at the landfill and what
needs to be done. Still concerns me a
little bit and this is a little bit off
the subject but it's a it's a subject
that the council is dealing with and
that is contractual services.
>> Well, one of them is for consulting on
the landfill seem like it's going very
well. is a previous director of
administration for this county under two
previous uh executives and he is
consulting. Well, if we are in such a a
mess with the landfill at this time,
I'm not sure I want somebody consulting
that's been involved in it for the
previous 10 years because
>> and you all are the council is is is
considering legislation to to put some
restrictions on how professional
services are awarded so that you all are
are much more uh up to date on how those
contracts are written. Correct.
>> Yeah. Generally, the council's not
informed of those contracts. Um, and and
we just we just want to be aware of
what's being written and for who and for
how long and and how much money. It's it
just boil basically boils down to fiscal
responsibility
>> in the scope of work, too, right? Yeah.
So, you could say, well, now it's done.
>> You know, we we find our ourselves um
scratching our heads asking some
questions like what's going on and and
we're just looking for a little bit uh
more information. Well, I I want to
bring Mike Goldberg in and I want to
talk more about your visit, my visit out
to the landfill and also the technical
side of the construction and just
because this is some of the work he's
done in his past career. So,
>> so stay with us. When we come back,
we're going to actually go through some
of the details of the construction phase
of Cell 7 out of the landfill and in
hopes to avoid a a phase closure. Stay
with us. We'll be right back.
Welcome back to open agenda and as we
said in the last segment we wanted to
talk a little bit more of the specifics
and the timeline of the construction
phase for for cell 7 out of the
landfill. In order to talk about that I
brought in Mr. Mike Goldberg from
Delmare and thank you for sticking
around Councilman Merritt.
>> Absolutely.
>> So uh you were at the work session on on
on Tuesday July 15th and you had a
chance to to see Adam Cory's
presentation. It was a very impressive
presentation right?
>> Yes it was. you know, our currently
introduced legislation, and we're not
going to dwell on that. Everybody's seen
it. Um, we're going to talk about the
refuge disposal permit and its language,
tonnage trends, where we've been in the
past 3 years, uh, out of county waste,
our history and recent timeline as far
as going back to where our, you know,
previous geocynch consultant uh,
volutric analysis that was performed.
We're going to talk about where we are
currently with volumetric analysis and
that leading up to the, you know, the
identification that we got an issue. we
got to address right now. Our current
operational status, what cell 7 looks
like on paper, horizontal expansion, and
then we'll wrap it all up for everybody.
>> I feel quite confident that Adam Corey
is the right man for the job, that the
problems out there are not originating
in him by any means.
>> Well, I I had a chance to go out last
Friday and do a tour with him. Uh he
invited me with my camera. In fact, I'm
going to air that interview separate
from this episode because I want to be
fair to that interview and I've talked
to PAC 14. They're going to drop that
interview separate from this show. It
will be like as an addendum and I
encourage people to see it.
>> But Councilman Mary, you also took your
own tour on Wednesday, July 16th, right
after the the presentation.
>> Yes.
>> And I want to hear a little bit about
what you what was your feedback. what
what was your sense after having been
out there with him?
>> So, I I wanted to uh go back out there.
Uh I took a tour right after we were all
sworn in and uh I invited uh Councilman
Enis, who just joined us on the council
to come with us. Uh we spent a lot of
time talking and asking questions and
getting answers and looking at things on
the computer, graphs and charts and and
documents. And uh uh I I agree that um
Mr. Cory is he knows what he's doing out
there.
>> Well, there was some things I saw that
and in and my background is agriculture,
you know, similar to environmental
science. U but we we pass the the
storage area for the used oil and for
the for the antifreeze. And one of the
things that's really key there is is
secondary containment. So, you know, you
hope that your your
>> your
>> bins never fail, but if they do, there
has to be a secondary way of keeping it
from spilling over.
>> Mhm. He showed me that and and and and
also a standing operating procedure if
there is a spill, which is really key. I
mean, you know, things will happen, but
you have to be prepared.
>> Uh we went up the hill and and I'm sure
you did as well.
>> We we looked down on the leech ponds and
there's two of them that were built in
the in the early 90s, but one of them is
drained all the way down, only has rain
water in it.
>> Yep.
>> That one actually failed u several
months ago and uh did not leak any uh
leech eight out. They they they worked
it out with the roads division in the
city of Salsbury
>> and they were able to to pump it out and
and get that processed like it should.
Uh and but we are down to one Lee pond
which is enough unless that one fails.
>> Um and then I I did get to go over to
the recycling center and see just how
well they're they're trying to redirect
as much refu out of the the landfill as
possible.
What was was there any takeaway besides
looking at cell 7 and cell 8 outside of
those two things that really kind of
took you by surprise?
>> Um it I was able to get a visual of how
much room is left.
>> Okay.
>> And you know we're not building a box
here. You know the cells they have to
slope. So,
you know, if you stand there and watch
them for a half an hour and one truck
right after the other going in there and
dumping and and then pushing and
packing,
it it's not hard to grasp how fast it
it's going to fill up.
>> You know, talking over at cell eight and
and uh you know, showing footage of of
of these two areas. So eight's where
they're working now and they're they're
building it up and and they can go up
all the way up to 220 ft but but they
had to have access to get up that high.
>> Yes.
>> Next to it like almost as a twin cell 7
which is at the corner of Nailaylor Mill
Road and Brick Kilm Road. So that's
actually the lowest point on that side
at this point.
>> Mhm. Uh he showed me where the the the
collection for the leech is is just he's
he's having to have it raised a few feet
so they don't have to dig out some old
trash, right?
>> That would then have to go into cell
seven or cell eight, sorry, which would
only fill it up faster.
>> Mike, this is where I want to ask you.
You've seen the plans for the the
construction of cell cell 7 with the
liner and the leech pumps and
>> not for cell 7. We haven't we have not
seen the plans that yet, but it's going
to be generally the same as the uh
construction drawings for cell number
eight. They're they're twins more or
less.
>> Okay. So, you've heard on this
presentation yesterday the timeline for
construction. Could you do a little
review of of what that's likely going to
look like?
>> Well, the uh the timeline is uh we have
to consider not just construction, but
design. Okay.
>> Drawings are somewhere between 75 and
90% complete. Now, my question is, and I
talked about this on last week's show,
that once you get to around the 80%
complete level on the construction
drawings, that's close enough to begin
the construction bidding process, but it
doesn't sound like it's going to start
for several more months. There could be
some reasons for that that I'm simply
unaware of.
>> I mean, he told me in my visit that he
hoped to get the the request for a
proposal out in August at some point. In
any event, once the construction
drawings are completed and all of the
necessary approvals and permits have
have been secured, uh the construction
phase, you know, will take somewhere
around a year and it really is
contingent on weather conditions. I I I
think they're looking at best case
scenario, worst case scenario could be a
whole another story. It could it could
delay the process uh completion of
construction for a number of months. We
just won't know until mother nature does
her thing this winter.
>> Did you get a chance to see uh the
saddle areas that that he was filling
in? I mean from cell 10 and cell 9. Yes.
They all kind of meet up with cell 8.
>> Mhm.
>> And and we're talking access point.
That's a little bit hard to understand.
I did get some footage out there,
>> but the you have to have a road to get
there. So, you can't just say, "Well,
we're going to airlift some trash and
just lay it there."
>> You have to have a road and then when
you have the road, then you have to take
the road back out. I I've heard anywhere
from 85 days to 120 days for
construction, but maybe a year,
especially if we don't know what the
weather conditions will be like. Mhm.
>> But it does sound like from my tour and
I'm wondering if you got the same
instance, Adam Cy is looking for
places, legal places in the airspace
from cell 9 and 10 and 8 once eight gets
built up
>> that they could maybe buy another 3 to
six months.
>> Mhm.
>> How do you feel like that fits into the
emergency legislation that you all are
trying to pass that may also address the
out ofount trash?
Well, again, the point of the emergency
legislation is to u allow the landfill
time to build the next cell and then
ultimately go into what's called the
horizontal expansion into the property
across the street
and
not have outofcount trash come in and
keep the landfill open all at the same
time because again,
>> now Mike, your your experience with
working with engineers uh construction
construction contracts doing due
diligence for bank work.
Time frames matter. Um you've you've had
a chance to listen to the presentation
and there we probably lost two years the
last most of the last two years to
getting cell 7 off the ground.
>> If you were financing this uh if you
were part of a group where would you be
looking to to to find out where that
that ball got dropped? Do you see any
any obvious signs?
>> I think it's the problem is very
obvious. The um the prior engineering
firm um who had prepared construction
drawings for other cells, a very
wellqualified uh firm has a terrific
reputation.
Um back in September of uh 2022,
they were ready to go. You know, the
>> Now that would have been just before the
county executive. would have been two
months before the county executive, the
current county executive, Miss G Miss
Gerardano, took office. Okay. But they
had already um created a project
schedule and that project schedule
provided for um uh engineering and
design to begin in the first quarter of
2023. Okay.
>> Well, that's not what happened. The
simple fact is we are approximately and
at least 18 months behind that schedule.
does not appear that the county
executive prioritized this important
project that impacts every single
resident of this county and now we're
dealing with the fallout from that.
>> Council mayor, what what is the next
step? I mean, you're going to have
another meeting. You you go three weeks
before you have your next meeting, the
first part of August.
>> What's going to happen at the next
meeting? Is this legislation? Is there
going to be a public hearing at that
point?
>> Not sure yet. We haven't set the agenda
for the next meeting yet.
>> Okay.
>> Yeah.
>> But it's going to come at some point in
August. It does. Yeah, it has to.
>> Do you know if if the county executive
is still planning on uh following
through with her phase closure on
Saturdays at the landfill starting in
August?
>> We were told that if we could um put
legislation in place that would remove
allowing out of county trash uh as a
possibility, then they would not be they
would not have closing the landfill as
an option.
>> But you won't be able to do that before
August 1st.
>> No. But the big question is what does
that resolve? All it does is create a
backlog of trash. What's not dumped
today is going to have to be dumped
tomorrow.
>> Closing the landfill is not going to
solve the problem.
>> I had a chance to ask Cory in my
interview last week and again that that
whole interview or that that interview
will be aired separately. Um you know he
he he really couldn't make a case that
it would diminish the amount of trash
unless we were to close it multiple
days. And that that wasn't supposed to
start till October 1st, but hopefully
>> before that we even get to that point
because it it being closed on a on a
Saturday and a Monday where it's already
closed on Sunday, that may be a public
health crisis in itself.
>> Well, that that would impact your your
restaurants. Uh you can imagine a high
volume restaurant having a busy weekend.
Imagine what that uh odor problem that
would cause on this plan. Are we going
to create a rodent problem which becomes
a health issue?
>> Philadelphia and New York would say yes.
Yeah.
>> Could we maybe catch back up with you in
another two months and just get a
followup to exactly what's going on? I
think uh I think having someone with
your your background and and your abil
your willingness to go out there and
find your own answers uh like to just
see what you've seen. Well, thank you
gentlemen and thanks for watching this
segment of Open Agenda. We'll be right
back.
>> Welcome back to Open Agenda. So, we've
had a chance to sit down with Councilman
Jeff Merritt and find out his take on
the work session and his tour of the
landfill uh after meeting with Adam
Corey. What questions do you still have
remaining, Jim? Well, I I think one of
the biggest things is how if they claim
that the 26% increase in the trash is
due to out of county people and they're
going to restrict out of county people
from dumping. I I find it a little hard
to comprehend that a quarter of our our
trash at the landfill is coming from out
of county. I'm I'm sure we have a good
amount that's coming, but but 25 26% a
lot of garbage coming from out of out of
county. So,
>> Mike, what questions do you still have
remaining?
>> Why did we get such a late start? I
think we know the answer to that and I
think we've, you know, developed uh the
answers to that question, you know,
throughout the discussion on this show
and that seems to to to ride on the
executive branch of of the county
government. Um, I also, um, would be
interested in finding if, uh, Mr.
Corey's design and construction schedule
is realistic. I think it's going to be
close. I think he's right. It's going to
be tight. The executive has claimed she
has full operational control and that
it's only the county council's job to
appropriate funds. Uh well, it's true
that she does have operational control
and therefore the administration is that
the culpability for this problem lies
with the administration. The county
council has granted all funding
requested by the executive branch of
government. Recently, up to I think it
was $10.5 million was bonded.
>> Yeah. The only the only thing the
council has turned down from the
executive's request for the past two
years with with the landfill has been
the tipping fees. And they haven't
turned them down. They have worked to
try to give some type of leadway or
notice to the the businesses, the
contractor haulers who have contracts
with municipalities and individual
homeowners that you know they need to
know in advance so they can set their
rates, not all of a sudden be told
>> two weeks from now we're going to raise
your rate. I have my own question and
and it comes from another item that was
on the agenda yesterday. Uh it was
discovered that the executives finance
department has has transferred $2.5
million without uh notification to the
council until after the fact. Now, my
understanding is legally that's all they
have to do.
>> Yes.
>> But we didn't know that we had a
landfill issue 30 days ago. When you see
that kind of number be be transferred
and a lot of it be transferred into the
pension fund, it makes me wonder what
else we don't know. So today, June 17 or
July 17th, it is the landfill, but
what's August 17th look like?
>> There's going to be something out there,
you know, from what from the history of
how this administration operates, how
they, you know, work behind closed
doors. They keep not only citizens in
the dark, but they keep our legislative
branch in the dark.
>> $2 and half million dollars is a lot of
money. And uh and a half a million of
that came from the roads department. And
I just remember about 18 months ago, the
executive's office was at the county
council asking for a million dollars to
pave off the road. And now we have a
half a million dollars not used in
paving
u in in in the fiscal year 24 that we
just wrapped up. I'm sorry, fiscal year
25 that we just wrapped up. And yet I
could I can take you down design road um
and and show you parts of roads that are
crumbling that are emergency access
roads. They're they're highly traveled.
So if we're if that's the if if we take
this landfill and then take this type of
action on other issues, could be funding
the pension fund, but it also could be
paving roads. We we don't know where
where this ends. Thank you gentlemen
both for coming in to speak with us.
Thanks for being at the meeting asking
good questions and uh we're going to
continue to follow the story and we'll
we'll follow back up in a few weeks as
as more details come out. Thanks for
watching this episode of Open Agenda.
We'll be back next week with another new
episode.
Can anybody do like a bad Jersey accent?

The County Executive's DERELICTION OF DUTY is revealed for all to see on this week's OPEN AGENDA (S2 E26). The Executive recently declared a crisis at the Newland Park Landfill because Cell #7 (currently being designed) may not be constructed before existing Cell #8 is filled. Although the Executive publicly promised to participate in a mid-July work session with the County Council to seek solutions, neither she nor her top decision makers bothered to show up. You'll also discover how the Executive failed to implement a plan to immediately begin design of Cell #7 that was put into place by her predecessor just two months before she took office in December 2022. As such, Cell #7 is at least 18 months behind schedule, hence the current crisis. She blames the problem on trash being brought in from outside the county, but for 2-1/2 years took no action to stop it. Bottom line: the Executive's failure to act is the cause of the current crisis, and she was AWOL when it came time to be part of the solution.